Work Tasks
The Following is a timeline for the work packages for the development of Thin Film PV-VG:-
Work Package 1
Project Management – (Month 1-24) Lead by University of Nottingham (UK)
Work Package 2
Thin Film PV VG component design and optimisation- Month (1-6)
Leader: University of Nottingham (UK) and Hubei University of Technology (China)
Work Package 3
Design, construction and testing of prototype (Month 7-15)
Leader: Vale Window Company Limited (UK) and Hanergy (China)
Work Package 4
Develop procedures & guidelines for manufacturing PV-VG in the UK and China
Leader: Solar Ready Company Limited (UK) and Hanergy (China)
Work Package 5
Field trials of PV-VG and monitoring under UK and China climatic conditions
Leader: Geo Green Power Limited (UK) and Hubei University of Technology (China)
Work Package 6
Certification and Analysis of the potential economic and environmental impacts
Leader: Solar Ready (UK) and Vale Window (UK) and Hanergy (China) and Hubei University of Technology (China)
Work Package 7
Dissemination and exploitation of project outcomes and knowledge transfer
Leader: University of Nottingham (UK) and Geo Green Power (UK) and Hubei University of Technology (China)