Work Tasks

Work

Packages

Work Tasks

The Following is a timeline for the work packages for the development of Thin Film PV-VG:-

Work Package 1

Project Management – (Month 1-24) Lead by University of Nottingham (UK)

Work Package 2

Thin Film PV VG component design and optimisation- Month (1-6)

Leader: University of Nottingham (UK) and Hubei University of Technology (China)

Work Package 3

Design, construction and testing of prototype (Month 7-15)

Leader: Vale Window Company Limited (UK) and Hanergy (China)

Work Package 4

Develop procedures & guidelines for manufacturing PV-VG in the UK and China

Leader: Solar Ready Company Limited (UK) and Hanergy (China)

Work Package 5

Field trials of PV-VG and monitoring under UK and China climatic conditions

Leader: Geo Green Power Limited (UK) and Hubei University of Technology (China)

Work Package 6

Certification and Analysis of the potential economic and environmental impacts

Leader: Solar Ready (UK) and Vale Window (UK) and Hanergy (China) and Hubei University of Technology (China)

Work Package 7

Dissemination and exploitation of project outcomes and knowledge transfer

Leader: University of Nottingham (UK) and Geo Green Power (UK) and Hubei University of Technology (China)

Project Exploitation Strategy